Malkajgiri Water Supply Scheme taken up under Municipal Development Project (MDP) with World Bank Assistance

HYDERABAD METROPOLITAN WATER SUPPLY AND SEWERAGE BOARD

Malkajgiri Water Supply Scheme taken up under

Municipal Development Project (MDP) with World Bank Assistance

 The Project was sanctioned vide GO MS.No.288 MA, dated: 21.4.2009 & GO Rt.No.1222 MA, dated: 27.8.2009, under MDP with World bank Assistance at a cost of Rs.338.55 Crores.

 

  • The funding pattern is Rs.236.98 Crores (70%) grant, Rs.67.71 Cr (20%) Loan under World Bank Assistance and Rs.33.85 Crs (10%) ULB Share.
  •  The project works were taken up in two packages as below. 

Package

Package

Contract Amount

Name of Agency

Package-I(a)

Construction of RCC GLSRs, ELSRs, Pump Houses in Malkajgiri Circle

Rs.57.52 Crores

M/s.Megha Engineering & Infrastructure Ltd., Hyderabad

Package-I(b)

Pipelines work for laying of feeder mains, distribution network in Malkajgiri Circle

Rs.181.14

Crores

M/s.IHP Co.Ltd.

Package-II

Supply Installation Commissioning of Central SCADA Station AMR Bulk & Domestic Water Meters in Malkajgiri Circle

Rs.41.30

Crores

(estimate cost)

Tender Stage

  •  The agreements were concluded during June’2014.
  • The project period is 24 months.
  • Most of the reservoir sites have been taken possession from the GHMC / Waqf Board.

 Physical Progress:

Reservoirs:

  • The total number of reservoirs to be built – 12 Nos
  • Its storage capacity – 45.70 ML
  • Individual reservoir capacity ranging from 700 KL  to 18 ML
  • 10 reservoir works are grounded. For remaining 2 reservoirs due to land constraint a combined GLSR is proposed.
  • All grounded reservoirs are in brisk progress and nearing completion.
  • Pump Houses at Sainikpuri, Vajpayee Nagar, Gauthamnagar & Moulali are in brisk progress and nearing completion.
  • It is programmed to complete and commission the reservoir in phased manner by Mar’2017.

 Pipelines:

  • The total length of pipeline to be laid is 386.50 Km.
  • The procurement of MS / DI pipelines for total length is completed.
  • Laying of pipeline network i.e. inlets, outlets and distribution mains is completed for a length of 353.7 Km. It is programmed to complete the laying of pipeline network by Mar’2017.

 

Malkajgiri Water Supply Scheme taken up under

Municipal Development Project (MDP) with World Bank Assistance


S.No

Reservoir Location

Capacity

Reservoir Type

1

Gautham Nagar  - GLSR

1.45 ML

GLSR

2

Defence Colony - ELSR

18.00 ML

GLSR

3

Tirumal Nagar - GLSR

5.00 ML

GLSR

4

Sainikpuri - ELSR

1.90 ML

ELSR

5

Moulali – ELSR

0.70 ML

ELSR

6

Vajpayee Nagar – ELSR

1.90 ML

ELSR

7

Vajpayee Nagar – ELSR

1.60 ML

ELSR

8

Sainathpuram (Geetha Nagar) – ELSR

1.45 ML

ELSR

9

Gautham Nagar – ELSR

2.90 ML

ELSR

10

Defence Colony – ELSR

1.40 ML

ELSR

 

 

 

 

 