WATER SUPPLY PROPOSALS TO THE VILLAGES SITUATED WITHIN ORR ON 27.11.2015

       In order to provide the required infrastructure of water supply to the villages within the ORR as per standards, the consultants are being engaged for preparation of DPR. EOI issued, RFP’s provided to the prospective consultants and last date for receipt of the offers is 30.11.2015.

      Meanwhile, detailed discussions were held with ‘RWS’ Engineers to assess the present water supply status in various villages. ‘RWS’ Engineers have provided the existing details of sumps, borewells, water supply distribution arrangements etc.

        Based on the inputs, HMWSSB is working out the further details required to meet the summer contingency and the long term proposals for construction of new reservoirs, inlet mains and distribution network. Tentative contingency plan under Calamity Relief Fund and non-CRF components, the proposals are prepared for Rs. 50 Crores for meeting the water supply crisis during ensuing summer. 