MD’S INSPECTION ON 29.09.2016

Sri.M.Dana Kishore, IAS, Managing Director, HMWSSB inspected some of the on-going work sites of construction of reservoirs under the Rs.1900 Crore HUDCO Aided Water Supply Improvement and Distribution Network in peripheral municipal circles here on Thursday 29th September 2016. He inspected the sites at Anjeya Nagar, Kukatpally, Hyderanagar, HUDA Park, Shaikpet.

Later, he held a review meeting on the progress of all the 56 reservoirs under the Project.

He instructed the agencies to expedite and complete the works as per time schedules. He also instructed the concerned Board Engineers to monitor the progress of works and submit weekly reports to Head Office.

He instructed to complete all the Inlet, Outlet works by October end 2016 and construction of reservoirs by February 2017. 

He viewed the live CC Camera’s coverage and interacted with Managers(Engg.) at work sites from Command Control Center, Board Office, Khairatabad.

Among others, who attended the meeting include Sri.M.Satyanarayana, Executive Director, Sri.M.Yellaswamy, Director(Projects), Sri.D.Sridhar Babu, Director(Revenue), Chief General Managers(Engg.), General Managers(Engg.), Projects Wing, HMWSSB.