READY FOR SEWERAGE MAINTENANCE ON 29.02.2020

Since a day is left over for taking over the sewerage maintenance from GHMC, Sri.M.Dana Kishore, IAS, Managing Director, HMWSSB has hold another round of discussion with concerned officers to kick start with all men and machinery. The officers informed the Managing Director stating that 584 sanitation staff, 66 mini Air tech machines, 28 Air tech machines with uniforms are ready to start the work from 1st March 2020.

The Managing Director has suggested the officers to get start the sewerage works by inviting local MLAs and other peoples representatives so as to have an idea about HMWSSB has taken over the maintenance from GHMC. 66 wards from 7 Municipalities, 3600 KMs length of pipeline, 3.26 lakh Manholes have come under HMWSSB from 1st March, 2020 

Dr.M.Satyanarayana, Executive Director, Directors and concerned CGMs, GMs, HMWSSB participated in the meeting