LAUNCH OF DRINKING WATER SUPPLY TO 60 COLONIES IN ORR-2 ON 20.04.2022

Sri.M.Dana Kishore, IAS, Managing Director, HMWSSB has reviewed the ORR Phase-2 works with officials of HMWSSB and construction companies on the progress of the pipelines and reservoirs on 20-04-2022.

Speaking on the occasion, the Managing Director said, the pipeline works have already been completed in 60 colonies under ORR Phase-2 areas and drinking water supply has also been started and directed the authorities to expedite the work in the other uncovered colonies as top priority to start water supply immediately.

He appealed the public who need new connections in these areas must get registered on the Water Board website and also said the water board is organizing special camps for registration of new connections where the pipeline works have already been completed and creating awareness among the people.

The Managing Director directed the officials concerned that the ORR Phase-2 works are to be completed by this December end. He said that the works are to be fasten and speeded up by adopting all safety measures for the workers at the work site.

Sri P. Ravi Kumar, Director Technical, M. Swamy, Director Operations, CGM’s, GM’s and officials from construction companies attended the meeting.

 