Projects Under Execution

Godavari Drinking Water Supply Project Phase-I

The Main Project cost is Rs.3375 Crores. GO No.679, dated: 26.9.2008. Ring Main Project Cost Rs.350 Crores. Total Project Cost Rs.3725 Crores (Rs.3375 Cr. + Rs.350 Cr.) Tenders called for in April’2008. Works awarded in Nov’2008.

Project funding is HUDCO Loan of Rs.2000 Crores and balance amount is from State Government budget.

The works are taken up in 3 packages on EPC. Contract value Rs.2861 Crores.

Project works are in brisk progress and status is as below.

Pipeline packages – 3 Packages Out of 186.62 Km, about 184.22 Km has been laid, balance 2.41 Km in progress.
Intake Channel well cum pump house(at Murmur) Phase-I - 10 TMC, Phase-II – 10 TMC Channel work complete, sump completed Pump house roof in progress.Pumps & motors to be erected.Sub-station completed.
Intermediate Reservoir & Pump House(at Bommakal) Reservoir work almost completed.Pump House roof slab in progress.Pumps & motors under erection.Sub-station completed.
WTP, Reservoir, Pump House(at Mallaram) 80% units nearing completion for 85 Mgd Reservoir work almost completed.Pump House completed Pumps & motors under erection.Sub-station completed.
Intermediate Reservoir & Pump House(at Kondapaka) Reservoir work completed.Pump House completed.Pumps & motors under erection.Sub-station completed.
Master Balancing Reservoir(at Ghanpur) Small reservoir nearing completion Main reservoir work in progress.
Ring Mains from MBR Ring Main-1 – Out of 37.56 Km, so far 27.76 Km laid. Balance 9.81 Km in progress.Ring Main-2 – Out of 29.67 Km, so far 19.96 Km laid. Balance 9.71 Km in progress.

Project will be completed by Aug’2015

Read More

Krishna Drinking Water Supply Project Phase-III

In view of increased water supply demand, the Krishna Phase-III project was sanctioned by the Government vide GO Ms.325 MA&UDD, dated: 24-8-2012, at a cost of Rs.1670 Crores to bring 90 Mgd from Krishna river.

The financial tie up was arranged with Rs.1500 Crores loan from HUDCO with the Government counter guarantee and the balance Rs.170 Crores from State Government Budget support.

The major component works are almost completed except one segment length of pipeline along PVNR Expressway in the city.

Pipeline packages – 6 Packages 4 packages 100% completed (ie 107 Km)2 Ring Main packages (63.5Km)–60.04 Km completed. Balance 3.45 Km.The Ring Main-2 of 28.13 Km is completedThe Ring Main-1 – 31.548 Km completed out of 35 Km. Balance 3.45 Km programmed for completion by June’2015.
Reservoirs – 1 Package 7 Nos - Completed
Pump Houses – 1 Package 4 Nos - Completed
Pumps & Motors – 1 Package Pumps, Motors, and Transformers erection completed
WTP – 1 Package 45 Mgd completed by April’2015 Balance 45 Mgd by 30th June’2015

Project partially commissioned for 45 Mgd in April’2015 and the 90 Mgd will be supplied with full commissioning by June’2015.

 

 

Read More

JNNURM Projects:

HMWSSB has taken up 11 projects under JnNURM at a cost of Rs.2002 Crores for improvement of water supply & sewerage infrastructure. Out of this, 8 projects are completed & commissioned and the balance 3 projects are nearing completion. The details are as below.

 

i. Water Supply Projects Taken up under JnNURM:

Sl.No.Name of ProjectProject Cost (Rs. In Crores)Remarks
1 Krishna Drinking Water Supply Project Phase-II 606.50 Completed
2 Pipeline Project from Sahebnagar to Prashasan Nagar 94.93 Completed
3 Pipeline Project from L.B.Nagar to Marredpally 81.20 Completed
4 Providing flow & level measures and SCADA System for all reservoirs and bulk supply mains in HMWSSB 9.90 Completed
5 Building Additional Storage Reservoirs on South of Musi – 49.50 ML at 7 locations 33.55 Completed
6 Building Additional Storage Reservoirs on North of Musi – 50.5 ML at 7 locations 29.81 Completed
7 Refurbishments of Existing Feeder System including Distribution network for the ten(10) zones in erstwhile MCH limits of Greater Hyderabad Municipal Corporation. 232.22 Completed
  Total 1088.11  

 

ii. Sewerage Projects Taken up under JnNURM:

Sl.No.Name of ProjectProject Cost (Rs. In Crores)Remarks
1 Rehabilitation and Strengthening of Sewerage System in Old City area on South of Musi -Zone –1 (in catchments S1 to S6, S12 and S14) 148.81 Completed
2. Rehabilitation and Strengthening of Sewerage System in Old City area on South of Musi - Zone – 2 (in catchments S7 to S11, S13 and S15) 251.25 Taken up in 3 packages. Two packages completed, one package nearing completion.
3. Implementation of Sewerage Master Plan in Serilingampally Circle of GHMC 200.38 Taken up in 3 packages. Two packages completed, one package nearing completion. Out of 4 STP works, two works completed & two works are in progress
4. Combined DPR for Improvement of Water Supply Distribution Network & Implementation of Sewerage Master Plan for taking up works in identified priority zones of Rajendranagar Circle 314.26 About 97% of project work is completed.
  Total 914.70  
  Grand Total (i & ii) 2002.81  

The balance works of 3 sewer projects are likely to be completed by June’2015.

Read More