The HMWS&S board has constructed about 2338 Rainwater Harvesting Structure(Recharge pits) with the volume of about 7900 Cum in the prmises of individual applicants.
Read MoreBrief Summary of HMWSSB Brochure Images HMWS&S board has constructed about 2338 Rainwater Harvesting Structure.
Read MoreMunicipal Administration and Urban Development Department Hyderabad Metropolitan water supply and sewerage Board Water Supply Distribution Network Project for Circles of Greater Hyderabad
Read MoreHUDCO/HRO Brochure Images Municipal Administration and Urban Development Department Hyderabad Metropolitan water supply and sewerage Board Water Supply Distribution Network Project for Circles of Greater Hyderabad
Read MoreAndhra pradesh Municipal Development Project(APMDP) Implementation of Comprehensive Water Supply Services improvements for malkajgiri municipality
Read MoreBrief Summary of malkajgiri municipal Andhra pradesh Municipal Development Project(APMDP)develoment project brochure images
Read MoreOngoing works in New innovations in HMWSSB …. As on 30-6-2017
HYDERABAD METROPOLITAN WATER SUPPLY AND SEWERAGE BOARD
Malkajgiri Water Supply Scheme taken up under
Municipal Development Project (MDP) with World Bank Assistance
The Project was sanctioned vide GO MS.No.288 MA, dated: 21.4.2009 & GO Rt.No.1222 MA, dated: 27.8.2009, under MDP with World bank Assistance at a cost of Rs.338.55 Crores.
Package |
Package |
Contract Amount |
Name of Agency |
Package-I(a) |
Construction of RCC GLSRs, ELSRs, Pump Houses in Malkajgiri Circle |
Rs.57.52 Crores |
M/s.Megha Engineering & Infrastructure Ltd., Hyderabad |
Package-I(b) |
Pipelines work for laying of feeder mains, distribution network in Malkajgiri Circle |
Rs.181.14 Crores |
M/s.IHP Co.Ltd. |
Package-II |
Supply Installation Commissioning of Central SCADA Station AMR Bulk & Domestic Water Meters in Malkajgiri Circle |
Rs.41.30 Crores (estimate cost) |
Tender Stage |
Physical Progress:
Reservoirs:
Pipelines:
Malkajgiri Water Supply Scheme taken up under
Municipal Development Project (MDP) with World Bank Assistance
S.No |
Reservoir Location |
Capacity |
Reservoir Type |
1 |
Gautham Nagar - GLSR |
1.45 ML |
GLSR |
2 |
Defence Colony - ELSR |
18.00 ML |
GLSR |
3 |
Tirumal Nagar - GLSR |
5.00 ML |
GLSR |
4 |
Sainikpuri - ELSR |
1.90 ML |
ELSR |
5 |
Moulali – ELSR |
0.70 ML |
ELSR |
6 |
Vajpayee Nagar – ELSR |
1.90 ML |
ELSR |
7 |
Vajpayee Nagar – ELSR |
1.60 ML |
ELSR |
8 |
Sainathpuram (Geetha Nagar) – ELSR |
1.45 ML |
ELSR |
9 |
Gautham Nagar – ELSR |
2.90 ML |
ELSR |
10 |
Defence Colony – ELSR |
1.40 ML |
ELSR |
HYDERABAD METROPOLITAN WATER SUPPLY AND SEWERAGE BOARD
Water Supply Distribution Network Project for the Peripheral Circles of GHMC
Package |
Package |
Contract Amount |
Name of Agency |
Package-I |
Construction of RCC Service Reservoirs and Providing Inlet, Outlet & Distribution network in Alwal, Kapra, Uppal&Ramachandrapuram Circles. |
Rs.539.32 crores |
M/s.Larsen& Toubro Ltd, Chennai |
Package-II |
Construction of RCC Service Reservoirs and Providing Inlet, Outlet & Distribution network in Quthubullapur, L.B.Nagar, Gaddiannaram, Rajendranagar Circles |
Rs.532.96 crores |
M/s.NCC Ltd, Hyderabad |
Package-III |
Construction of RCC Service Reservoirs and Providing Inlet,Outlet& Distribution network in Kukatpally, Serilingampally, Patancheru Circles |
Rs.561.32 crores |
M/s.Megha Engineering Infrastructure Ltd, Hyderabad |
Physical Progress:
Reservoirs:
Pipelines:
Water Supply Distribution Network Project for the Peripheral Circles of GHMC
PACKAGE -I:
Sl.No. |
|
Reservoir Location |
Capacity |
Reservoir Type |
I |
UPPAL CIRCLE |
|||
1 |
1 |
Elugutta-GLSR |
13.30 |
GLSR |
2 |
2 |
NGRI-ELSR |
1.00 |
ELSR |
3 |
3 |
Chilkanagar- GLSR |
1.00 |
GLSR |
4 |
4 |
Gokhelnagar-ELSR |
1.00 |
ELSR |
II |
KAPRA CIRCLE |
|||
5 |
1 |
Radhika, AS.Rao Nagar- GLSR |
7.00 |
GLSR |
6 |
2 |
Kailasgiri-GLSR |
5.00 |
GLSR |
7 |
3 |
OUT Colony-GLSR |
7.00 |
GLSR |
8 |
4 |
ECIL Zone-GLSR |
7.50 |
GLSR |
9 |
5 |
Snehapuri Zone- GLSR |
6.50 |
GLSR |
10 |
6 |
Gopal Reddy Nagar- GLSR (Vijayapuri Colony) |
2.00 |
GLSR |
III |
ALWAL CIRCLE |
|||
11 |
1 |
Alwal Reservoir I-GLSR |
22.50 |
GLSR |
12 |
2 |
Alwal Reservoir II-ELSR |
2.00 |
ELSR |
13 |
3 |
Yapral-ELSR |
1.50 |
ELSR |
14 |
4 |
Kowkoor- ELSR |
2.00 |
ELSR |
15 |
5 |
Jonnabanda-ELSR (Machha Bollaram(v)) |
1.50 |
ELSR |
16 |
6 |
Jonnabanda-GLSR (Machha Bollaram(v)) |
9.00 |
GLSR |
IV |
RAMACHANDRAPURAM CIRCLE |
|||
17 |
1 |
LIG Quarters (BHEL)-ELSR |
2.50 |
ELSR |
18 |
2 |
MIG Quarters (BHEL)-ELSR |
2.50 |
ELSR |
19 |
3 |
Ashok Nagar-GLSR |
2.50 |
ELSR |
PACKAGE-II:
Sl.No. |
|
Reservoir Location |
Capacity |
Reservoir Type |
V |
QUTHUBULLAPUR CIRCLE |
|||
20 |
1 |
Suraram-GLSR |
7.50 |
GLSR |
21 |
2 |
Chintal-GLSR |
4.00 |
GLSR |
22 |
3 |
Shapoornagar-GLSR |
6.00 |
GLSR |
23 |
4 |
Jagadgirigutta-GLSR |
7.00 |
GLSR |
24 |
5 |
Gajularamaram-GLSR |
2.00 |
GLSR |
25 |
6 |
Alwal-ELSR |
1.00 |
ELSR |
VI |
LB NAGAR, GADDINARRAM & RAJENDRANAGAR |
|||
26 |
1 |
Rythu Bazar-I ELSR |
2.00 |
ELSR |
27 |
2 |
Sahebnagar ELSR |
1.00 |
ELSR |
28 |
3 |
Red Tank, Sachivalayan Nagar- ELSR |
2.00 |
ELSR |
29 |
4 |
White Tank, Prasanthi Nagar-I ELSR |
2.00 |
ELSR |
30 |
5 |
White Tank, Prasanthi Nagar-II ELSR |
1.00 |
ELSR |
31 |
6 |
Green Tank, Vaidehi Nagar-I, ELSR |
2.50 |
ELSR |
32 |
7 |
Green Tank, Vaidehi Nagar-II, ELSR |
1.00 |
ELSR |
33 |
8 |
Auto Nagar- GLSR |
6.00 |
GLSR |
34 |
9 |
Sahebnagar-GLSR |
22.00 |
GLSR |
35 |
10 |
Kothapet, Vasavi Nagar- ELSR |
2.50 |
ELSR |
36 |
11 |
Rocktown, Vasavi Nagar- ELSR |
2.50 |
ELSR |
37 |
12 |
Hayathnagar |
4.00 |
GLSR |
38 |
13 |
Madhubhan, Rajendernagar- GLSR |
9.00 |
GLSR |
PACKAGE-III:
Sl. No. |
|
Reservoir Location |
Capacity |
Reservoir Type |
VII |
SERILINGAMPALLY |
|||
39 |
1 |
HUDA Miyapur-GLSR |
6.00 |
GLSR |
40 |
2 |
Vigyan Vidyalaya (Ayyappa Society)- GLSR |
4.00 |
GLSR |
41 |
3 |
Gopanpally GLSR |
2.50 |
GLSR |
42 |
4 |
Doyens Colony GLSR |
8.00 |
GLSR |
43 |
5 |
Deepthi Sree Nagar GLSR |
4.00 |
GLSR |
44 |
6 |
HCU, Nalagandla-GLSR |
3.00 |
GLSR |
45 |
7 |
IIIT (Sachivalayan Nagar)-GLSR |
2.50 |
GLSR |
46 |
8 |
Lingampally- ELSR |
2.00 |
ELSR |
47 |
9 |
Haffezpet –GLSR |
6.00 |
GLSR |
48 |
10 |
Suraksha Hills |
3.00 |
GLSR |
49 |
11 |
Kondapur (Masid Banda) |
2.00 |
GLSR |
VIII |
KUKATPALLY CIRCLE |
|||
50 |
1 |
Hyderanagar-GLSR |
14.00 |
GLSR |
51 |
2 |
Kukatpally GLSR (Dn-IX Premises for HUDA Park Zone) |
3.50 |
GLSR |
52 |
3 |
KPHB Ph-IV GLSR |
2.50 |
GLSR |
53 |
4 |
Yellammabanda – GLSR |
7.00 |
GLSR |
54 |
5 |
Anjaneya Nagar- ELSR (Kukatpally Mpl Office) 2x2.00 |
4.00 |
ELSR |
55 |
6 |
Shapoornagar-GLSR (IDPL Zone) |
7.75 |
GLSR |
IX |
PATANCHERU CIRCLE |
|||
56 |
1 |
Patancheruvu -GLSR (HMWSSB Premises) |
15.00 |
GLSR |
The Main Project cost is Rs.3375 Crores. GO No.679, dated: 26.9.2008. Ring Main Project Cost Rs.350 Crores. Total Project Cost Rs.3725 Crores (Rs.3375 Cr. + Rs.350 Cr.) Tenders called for in April’2008. Works awarded in Nov’2008.
Project funding is HUDCO Loan of Rs.2000 Crores and balance amount is from State Government budget.
The works are taken up in 3 packages on EPC. Contract value Rs.2861 Crores.
Project works are in brisk progress and status is as below.
Pipeline packages – 3 Packages | Out of 186.62 Km, about 184.22 Km has been laid, balance 2.41 Km in progress. |
Intake Channel well cum pump house(at Murmur) | Phase-I - 10 TMC, Phase-II – 10 TMC Channel work complete, sump completed Pump house roof in progress.Pumps & motors to be erected.Sub-station completed. |
Intermediate Reservoir & Pump House(at Bommakal) | Reservoir work almost completed.Pump House roof slab in progress.Pumps & motors under erection.Sub-station completed. |
WTP, Reservoir, Pump House(at Mallaram) | 80% units nearing completion for 85 Mgd Reservoir work almost completed.Pump House completed Pumps & motors under erection.Sub-station completed. |
Intermediate Reservoir & Pump House(at Kondapaka) | Reservoir work completed.Pump House completed.Pumps & motors under erection.Sub-station completed. |
Master Balancing Reservoir(at Ghanpur) | Small reservoir nearing completion Main reservoir work in progress. |
Ring Mains from MBR | Ring Main-1 – Out of 37.56 Km, so far 27.76 Km laid. Balance 9.81 Km in progress.Ring Main-2 – Out of 29.67 Km, so far 19.96 Km laid. Balance 9.71 Km in progress. |
Project will be completed by Aug’2015
In view of increased water supply demand, the Krishna Phase-III project was sanctioned by the Government vide GO Ms.325 MA&UDD, dated: 24-8-2012, at a cost of Rs.1670 Crores to bring 90 Mgd from Krishna river.
The financial tie up was arranged with Rs.1500 Crores loan from HUDCO with the Government counter guarantee and the balance Rs.170 Crores from State Government Budget support.
The major component works are almost completed except one segment length of pipeline along PVNR Expressway in the city.
Pipeline packages – 6 Packages | 4 packages 100% completed (ie 107 Km)2 Ring Main packages (63.5Km)–60.04 Km completed. Balance 3.45 Km.The Ring Main-2 of 28.13 Km is completedThe Ring Main-1 – 31.548 Km completed out of 35 Km. Balance 3.45 Km programmed for completion by June’2015. |
Reservoirs – 1 Package | 7 Nos - Completed |
Pump Houses – 1 Package | 4 Nos - Completed |
Pumps & Motors – 1 Package | Pumps, Motors, and Transformers erection completed |
WTP – 1 Package | 45 Mgd completed by April’2015 Balance 45 Mgd by 30th June’2015 |
Project partially commissioned for 45 Mgd in April’2015 and the 90 Mgd will be supplied with full commissioning by June’2015.
HMWSSB has taken up 11 projects under JnNURM at a cost of Rs.2002 Crores for improvement of water supply & sewerage infrastructure. Out of this, 8 projects are completed & commissioned and the balance 3 projects are nearing completion. The details are as below.
Sl.No. | Name of Project | Project Cost (Rs. In Crores) | Remarks |
---|---|---|---|
1 | Krishna Drinking Water Supply Project Phase-II | 606.50 | Completed |
2 | Pipeline Project from Sahebnagar to Prashasan Nagar | 94.93 | Completed |
3 | Pipeline Project from L.B.Nagar to Marredpally | 81.20 | Completed |
4 | Providing flow & level measures and SCADA System for all reservoirs and bulk supply mains in HMWSSB | 9.90 | Completed |
5 | Building Additional Storage Reservoirs on South of Musi – 49.50 ML at 7 locations | 33.55 | Completed |
6 | Building Additional Storage Reservoirs on North of Musi – 50.5 ML at 7 locations | 29.81 | Completed |
7 | Refurbishments of Existing Feeder System including Distribution network for the ten(10) zones in erstwhile MCH limits of Greater Hyderabad Municipal Corporation. | 232.22 | Completed |
Total | 1088.11 |
Sl.No. | Name of Project | Project Cost (Rs. In Crores) | Remarks |
---|---|---|---|
1 | Rehabilitation and Strengthening of Sewerage System in Old City area on South of Musi -Zone –1 (in catchments S1 to S6, S12 and S14) | 148.81 | Completed |
2. | Rehabilitation and Strengthening of Sewerage System in Old City area on South of Musi - Zone – 2 (in catchments S7 to S11, S13 and S15) | 251.25 | Taken up in 3 packages. Two packages completed, one package nearing completion. |
3. | Implementation of Sewerage Master Plan in Serilingampally Circle of GHMC | 200.38 | Taken up in 3 packages. Two packages completed, one package nearing completion. Out of 4 STP works, two works completed & two works are in progress |
4. | Combined DPR for Improvement of Water Supply Distribution Network & Implementation of Sewerage Master Plan for taking up works in identified priority zones of Rajendranagar Circle | 314.26 | About 97% of project work is completed. |
Total | 914.70 | ||
Grand Total (i & ii) | 2002.81 |
The balance works of 3 sewer projects are likely to be completed by June’2015.
English A+ AA- A A
24గం. వినియోగదారుల సేవా కేంద్రం: 155 313
040- 23300114 & 23433933
customer-support@hyderabadwater.gov.in