Projects

Projects Under Execution

Brief Summary of HMWSSB

The HMWS&S board has constructed about 2338 Rainwater Harvesting Structure(Recharge pits) with the volume of about 7900 Cum in the prmises of individual applicants.

Read More

Brief Summary of HMWSSB Brochure Images

Brief Summary of HMWSSB Brochure Images HMWS&S board has constructed about 2338 Rainwater Harvesting Structure.

Read More

HUDCO/HRO Water Supply of HMWSSB

Municipal Administration and Urban Development Department Hyderabad Metropolitan water supply and sewerage Board Water Supply Distribution Network Project for Circles of Greater Hyderabad

Read More

HUDCO/HRO Brochure Images

HUDCO/HRO Brochure Images Municipal Administration and Urban Development Department Hyderabad Metropolitan water supply and sewerage Board Water Supply Distribution Network Project for Circles of Greater Hyderabad

Read More

Brief Summary of malkajgiri municipal development project

Andhra pradesh Municipal Development Project(APMDP) Implementation of Comprehensive Water Supply Services improvements for malkajgiri municipality

Read More

Brief Summary of malkajgiri municipal develoment project brochure images

Brief Summary of malkajgiri municipal Andhra pradesh Municipal Development Project(APMDP)develoment project brochure images

Read More

New innovations in HMWSSB

Uploded Date: Start Date: End Date: Office Type: Office-1

Ongoing works in New innovations in HMWSSB …. As on 30-6-2017

Full Details

Malkajgiri Water Supply Scheme taken up under Municipal Development Project (MDP) with World Bank Assistance

HYDERABAD METROPOLITAN WATER SUPPLY AND SEWERAGE BOARD

Malkajgiri Water Supply Scheme taken up under

Municipal Development Project (MDP) with World Bank Assistance

 The Project was sanctioned vide GO MS.No.288 MA, dated: 21.4.2009 & GO Rt.No.1222 MA, dated: 27.8.2009, under MDP with World bank Assistance at a cost of Rs.338.55 Crores.

 

  • The funding pattern is Rs.236.98 Crores (70%) grant, Rs.67.71 Cr (20%) Loan under World Bank Assistance and Rs.33.85 Crs (10%) ULB Share.
  •  The project works were taken up in two packages as below. 

Package

Package

Contract Amount

Name of Agency

Package-I(a)

Construction of RCC GLSRs, ELSRs, Pump Houses in Malkajgiri Circle

Rs.57.52 Crores

M/s.Megha Engineering & Infrastructure Ltd., Hyderabad

Package-I(b)

Pipelines work for laying of feeder mains, distribution network in Malkajgiri Circle

Rs.181.14

Crores

M/s.IHP Co.Ltd.

Package-II

Supply Installation Commissioning of Central SCADA Station AMR Bulk & Domestic Water Meters in Malkajgiri Circle

Rs.41.30

Crores

(estimate cost)

Tender Stage

  •  The agreements were concluded during June’2014.
  • The project period is 24 months.
  • Most of the reservoir sites have been taken possession from the GHMC / Waqf Board.

 Physical Progress:

Reservoirs:

  • The total number of reservoirs to be built – 12 Nos
  • Its storage capacity – 45.70 ML
  • Individual reservoir capacity ranging from 700 KL  to 18 ML
  • 10 reservoir works are grounded. For remaining 2 reservoirs due to land constraint a combined GLSR is proposed.
  • All grounded reservoirs are in brisk progress and nearing completion.
  • Pump Houses at Sainikpuri, Vajpayee Nagar, Gauthamnagar & Moulali are in brisk progress and nearing completion.
  • It is programmed to complete and commission the reservoir in phased manner by Mar’2017.

 Pipelines:

  • The total length of pipeline to be laid is 386.50 Km.
  • The procurement of MS / DI pipelines for total length is completed.
  • Laying of pipeline network i.e. inlets, outlets and distribution mains is completed for a length of 353.7 Km. It is programmed to complete the laying of pipeline network by Mar’2017.

 

Malkajgiri Water Supply Scheme taken up under

Municipal Development Project (MDP) with World Bank Assistance


S.No

Reservoir Location

Capacity

Reservoir Type

1

Gautham Nagar  - GLSR

1.45 ML

GLSR

2

Defence Colony - ELSR

18.00 ML

GLSR

3

Tirumal Nagar - GLSR

5.00 ML

GLSR

4

Sainikpuri - ELSR

1.90 ML

ELSR

5

Moulali – ELSR

0.70 ML

ELSR

6

Vajpayee Nagar – ELSR

1.90 ML

ELSR

7

Vajpayee Nagar – ELSR

1.60 ML

ELSR

8

Sainathpuram (Geetha Nagar) – ELSR

1.45 ML

ELSR

9

Gautham Nagar – ELSR

2.90 ML

ELSR

10

Defence Colony – ELSR

1.40 ML

ELSR

 

 

 

 

 


Read More

HUDCO Project for Water Supply Distribution Network in the Peripheral Circles of GHMC

HYDERABAD METROPOLITAN WATER SUPPLY AND SEWERAGE BOARD

Water Supply Distribution Network Project for the Peripheral Circles of GHMC

  • The Government has accorded administrative sanction for the “Water Supply Distribution Network Project for the Peripheral Circles of Greater Hyderabad Municipal Corporation” at an estimated cost of Rs.1900 crores vide GO.Ms.No.138, MA&UD(UBS) Department dated 21.10.2015
  •  The Project funding is with Rs.1700 crores HUDCO Loan and Rs.200 crores through State Government budgetary support. 
  • The project works were taken up in three packages as below. 

Package

Package

Contract Amount

Name of Agency

Package-I

Construction of RCC Service Reservoirs and Providing Inlet, Outlet & Distribution network in Alwal, Kapra, Uppal&Ramachandrapuram Circles.

Rs.539.32 crores

M/s.Larsen& Toubro Ltd, Chennai

Package-II

Construction of RCC Service Reservoirs and Providing Inlet, Outlet & Distribution network in Quthubullapur, L.B.Nagar, Gaddiannaram, Rajendranagar Circles

Rs.532.96 crores

M/s.NCC Ltd, Hyderabad

Package-III

Construction of RCC Service Reservoirs and Providing Inlet,Outlet& Distribution network in Kukatpally, Serilingampally, Patancheru Circles

Rs.561.32 crores

M/s.Megha Engineering Infrastructure Ltd, Hyderabad

 

  • The agreements were concluded during Feb’2016
  • The Project period is 24 months.
  • Most of the reservoir sites have been taken possession from the GHMC, Collector, R.R.District
  • Two reservoir sites at Kowkur& Jonnabanda are yet to be received.

 Physical Progress:

Reservoirs:

  • The total number of reservoirs to be built – 56 Nos.
  • Its storage capacity-279-ML
  • Individual reservoir capacity ranging from 1 ML to 22.5 ML.
  • 54 reservoir works are grounded.  For 2 reservoirs i.e,. at Kowkur& Jonnabanda, land yet to be transferred from Collector, R.R.District.
  • All grounded reservoir works are in brisk progress.
  • It is programmed to complete and commission the reservoir in phased manner.

 Pipelines:

  • The total length of pipeline to be laid in 2600 Km.  The procurement of MS/DI pipelines is in progress.
  • Inlet Mains: It is programmed to complete the laying of inlet mains in phased manner.
  • Outlet and Distribution mains: It is programmed to complete the laying of outlet & distribution mains in phased manner. 


Water Supply Distribution Network Project for the Peripheral Circles of GHMC

 

PACKAGE -I: 

Sl.No.

 

Reservoir Location

Capacity

Reservoir Type

I

UPPAL CIRCLE  

1

1

Elugutta-GLSR

13.30

GLSR

2

2

NGRI-ELSR

1.00

ELSR

3

3

Chilkanagar- GLSR

1.00

GLSR

4

4

Gokhelnagar-ELSR

1.00

ELSR

II

KAPRA CIRCLE  

5

1

Radhika, AS.Rao Nagar- GLSR

7.00

GLSR

6

2

Kailasgiri-GLSR

5.00

GLSR

7

3

OUT Colony-GLSR

7.00

GLSR

8

4

ECIL Zone-GLSR

7.50

GLSR

9

5

Snehapuri Zone- GLSR

6.50

GLSR

10

6

Gopal Reddy Nagar- GLSR (Vijayapuri Colony)

2.00

GLSR

III

ALWAL CIRCLE  

11

1

Alwal Reservoir I-GLSR

22.50

GLSR

12

2

Alwal Reservoir II-ELSR

2.00

ELSR

13

3

Yapral-ELSR

1.50

ELSR

14

4

Kowkoor- ELSR

2.00

ELSR

15

5

Jonnabanda-ELSR (Machha Bollaram(v))

1.50

ELSR

16

6

Jonnabanda-GLSR (Machha Bollaram(v))

9.00

GLSR

IV

RAMACHANDRAPURAM CIRCLE  

17

1

LIG Quarters (BHEL)-ELSR

2.50

ELSR

18

2

MIG Quarters (BHEL)-ELSR

2.50

ELSR

19

3

Ashok Nagar-GLSR

2.50

ELSR

    


PACKAGE-II: 

Sl.No.

 

Reservoir Location

Capacity

Reservoir Type

V

QUTHUBULLAPUR CIRCLE 

20

1

Suraram-GLSR

7.50

GLSR

21

2

Chintal-GLSR

4.00

GLSR

22

3

Shapoornagar-GLSR

6.00

GLSR

23

4

Jagadgirigutta-GLSR

7.00

GLSR

24

5

Gajularamaram-GLSR

2.00

GLSR

25

6

Alwal-ELSR

1.00

ELSR

VI

LB NAGAR, GADDINARRAM & RAJENDRANAGAR   

26

1

Rythu Bazar-I ELSR

2.00

ELSR

27

2

Sahebnagar ELSR

1.00

ELSR

28

3

Red Tank, Sachivalayan Nagar- ELSR

2.00

ELSR

29

4

White Tank, Prasanthi Nagar-I ELSR

2.00

ELSR

30

5

White Tank, Prasanthi Nagar-II ELSR

1.00

ELSR

31

6

Green Tank, Vaidehi Nagar-I, ELSR

2.50

ELSR

32

7

Green Tank, Vaidehi Nagar-II, ELSR

1.00

ELSR

33

8

Auto Nagar- GLSR

6.00

GLSR

34

9

Sahebnagar-GLSR

22.00

GLSR

35

10

Kothapet, Vasavi Nagar- ELSR

2.50

ELSR

36

11

Rocktown, Vasavi Nagar- ELSR

2.50

ELSR

37

12

Hayathnagar

4.00

GLSR

38

13

Madhubhan, Rajendernagar- GLSR

9.00

GLSR

 


PACKAGE-III: 

Sl.

No.

 

Reservoir Location

Capacity

Reservoir Type

VII

SERILINGAMPALLY

39

1

HUDA Miyapur-GLSR

6.00

GLSR

40

2

Vigyan Vidyalaya (Ayyappa Society)- GLSR

4.00

GLSR

41

3

Gopanpally GLSR

2.50

GLSR

42

4

Doyens Colony GLSR

8.00

GLSR

43

5

Deepthi Sree Nagar GLSR

4.00

GLSR

44

6

HCU, Nalagandla-GLSR

3.00

GLSR

45

7

IIIT (Sachivalayan Nagar)-GLSR

2.50

GLSR

46

8

Lingampally- ELSR

2.00

ELSR

47

9

Haffezpet –GLSR

6.00

GLSR

48

10

Suraksha Hills

3.00

GLSR

49

11

Kondapur (Masid Banda)

2.00

GLSR

VIII

KUKATPALLY CIRCLE

50

1

Hyderanagar-GLSR

14.00

GLSR

51

2

Kukatpally GLSR (Dn-IX Premises for HUDA Park Zone)

3.50

GLSR

52

3

KPHB Ph-IV GLSR

2.50

GLSR

53

4

Yellammabanda – GLSR

7.00

GLSR

54

5

Anjaneya Nagar- ELSR (Kukatpally Mpl Office) 2x2.00

4.00

ELSR

55

6

Shapoornagar-GLSR (IDPL Zone)

7.75

GLSR

IX

PATANCHERU CIRCLE

56

1

Patancheruvu -GLSR (HMWSSB Premises)

15.00

GLSR

 

 

 


Read More

Godavari Drinking Water Supply Project Phase-I

The Main Project cost is Rs.3375 Crores. GO No.679, dated: 26.9.2008. Ring Main Project Cost Rs.350 Crores. Total Project Cost Rs.3725 Crores (Rs.3375 Cr. + Rs.350 Cr.) Tenders called for in April’2008. Works awarded in Nov’2008.

Project funding is HUDCO Loan of Rs.2000 Crores and balance amount is from State Government budget.

The works are taken up in 3 packages on EPC. Contract value Rs.2861 Crores.

Project works are in brisk progress and status is as below.

Pipeline packages – 3 Packages Out of 186.62 Km, about 184.22 Km has been laid, balance 2.41 Km in progress.
Intake Channel well cum pump house(at Murmur) Phase-I - 10 TMC, Phase-II – 10 TMC Channel work complete, sump completed Pump house roof in progress.Pumps & motors to be erected.Sub-station completed.
Intermediate Reservoir & Pump House(at Bommakal) Reservoir work almost completed.Pump House roof slab in progress.Pumps & motors under erection.Sub-station completed.
WTP, Reservoir, Pump House(at Mallaram) 80% units nearing completion for 85 Mgd Reservoir work almost completed.Pump House completed Pumps & motors under erection.Sub-station completed.
Intermediate Reservoir & Pump House(at Kondapaka) Reservoir work completed.Pump House completed.Pumps & motors under erection.Sub-station completed.
Master Balancing Reservoir(at Ghanpur) Small reservoir nearing completion Main reservoir work in progress.
Ring Mains from MBR Ring Main-1 – Out of 37.56 Km, so far 27.76 Km laid. Balance 9.81 Km in progress.Ring Main-2 – Out of 29.67 Km, so far 19.96 Km laid. Balance 9.71 Km in progress.

Project will be completed by Aug’2015

Read More

Krishna Drinking Water Supply Project Phase-III

In view of increased water supply demand, the Krishna Phase-III project was sanctioned by the Government vide GO Ms.325 MA&UDD, dated: 24-8-2012, at a cost of Rs.1670 Crores to bring 90 Mgd from Krishna river.

The financial tie up was arranged with Rs.1500 Crores loan from HUDCO with the Government counter guarantee and the balance Rs.170 Crores from State Government Budget support.

The major component works are almost completed except one segment length of pipeline along PVNR Expressway in the city.

Pipeline packages – 6 Packages 4 packages 100% completed (ie 107 Km)2 Ring Main packages (63.5Km)–60.04 Km completed. Balance 3.45 Km.The Ring Main-2 of 28.13 Km is completedThe Ring Main-1 – 31.548 Km completed out of 35 Km. Balance 3.45 Km programmed for completion by June’2015.
Reservoirs – 1 Package 7 Nos - Completed
Pump Houses – 1 Package 4 Nos - Completed
Pumps & Motors – 1 Package Pumps, Motors, and Transformers erection completed
WTP – 1 Package 45 Mgd completed by April’2015 Balance 45 Mgd by 30th June’2015

Project partially commissioned for 45 Mgd in April’2015 and the 90 Mgd will be supplied with full commissioning by June’2015.

 

 

Read More

JNNURM Projects:

HMWSSB has taken up 11 projects under JnNURM at a cost of Rs.2002 Crores for improvement of water supply & sewerage infrastructure. Out of this, 8 projects are completed & commissioned and the balance 3 projects are nearing completion. The details are as below.

 

i. Water Supply Projects Taken up under JnNURM:

Sl.No.Name of ProjectProject Cost (Rs. In Crores)Remarks
1 Krishna Drinking Water Supply Project Phase-II 606.50 Completed
2 Pipeline Project from Sahebnagar to Prashasan Nagar 94.93 Completed
3 Pipeline Project from L.B.Nagar to Marredpally 81.20 Completed
4 Providing flow & level measures and SCADA System for all reservoirs and bulk supply mains in HMWSSB 9.90 Completed
5 Building Additional Storage Reservoirs on South of Musi – 49.50 ML at 7 locations 33.55 Completed
6 Building Additional Storage Reservoirs on North of Musi – 50.5 ML at 7 locations 29.81 Completed
7 Refurbishments of Existing Feeder System including Distribution network for the ten(10) zones in erstwhile MCH limits of Greater Hyderabad Municipal Corporation. 232.22 Completed
  Total 1088.11  

 

ii. Sewerage Projects Taken up under JnNURM:

Sl.No.Name of ProjectProject Cost (Rs. In Crores)Remarks
1 Rehabilitation and Strengthening of Sewerage System in Old City area on South of Musi -Zone –1 (in catchments S1 to S6, S12 and S14) 148.81 Completed
2. Rehabilitation and Strengthening of Sewerage System in Old City area on South of Musi - Zone – 2 (in catchments S7 to S11, S13 and S15) 251.25 Taken up in 3 packages. Two packages completed, one package nearing completion.
3. Implementation of Sewerage Master Plan in Serilingampally Circle of GHMC 200.38 Taken up in 3 packages. Two packages completed, one package nearing completion. Out of 4 STP works, two works completed & two works are in progress
4. Combined DPR for Improvement of Water Supply Distribution Network & Implementation of Sewerage Master Plan for taking up works in identified priority zones of Rajendranagar Circle 314.26 About 97% of project work is completed.
  Total 914.70  
  Grand Total (i & ii) 2002.81  

The balance works of 3 sewer projects are likely to be completed by June’2015.

Read More