S.NoName of the WorkEstimateO&M CircleO&M DivisionDateStatus
1 Laying of 100mm dia DI pipeline for providing WS to M/S Vircho Chemical Private Limited tapping 150mm dia AC main near Telephone Exchange 6.00 Circle-4 Division-8 23-Apr-08 Tender Process
2 Laying of 100mm dia DI pipeline off-take arrangement and fixing of 40mm dia Water Meter for providing WS to M/S Ushodaya Towers Flats Owners Association from Ph-I 900mm dia Pumping Main tapping at Scour Chamber at Ch. 1197.50 9.50 Circle-4 Division-8 21-May-08 Tender Process
3 Rectification of pipe burst leakage on 1500mm dia PSC pumping main from Kalabgoor to Patancheru at Ch. 331 near Kandhi Vill 1.59 Circle-4 Division-8 13-May-08 Tender Process
4 Rectification of heavy leakage on 1500mm dia Ph-II PSC Pumping Main from Kalabgoor to Patancheru at Ch. 97, near Angadipet Village 1.66 Circle-4 Division-8 13-May-08 Tender Process
5 Rectification of pipe burst leakage on 1500mm dia PSC pumping main from Kalabgur to Patancheru at Ch. 780.0, near Muthangi Village 1.61 Circle-4 Division-8 13-May-08 Tender Process
6 Removing of existing 1500mm dia MS pipe 200mm dia Sluice Valve and fixing of 200mm dia new Sluice Valve and 300mm dia MS pipe and 200mm dia MS Specials and dummy plate at Phase-II Pumping Main, opposite to Jyothi Theatre 3.45 Circle-4 Division-8 24-Jun-08 Tender Process
7 Rectification of heavy leakage on 1500mm dia Ph-II PSC Pumping Main at Ch. 279, near Gullaguda Deck 0.20 Circle-4 Division-8 13-May-08 Progress
8 Rectification of heavy leakage on 1500mm dia Ph. II PSC pumping main at Ch.781, near Muthangi Village 0.16 Circle-4 Division-8 13-May-08 Progress
9 Rectification of heavy leakages on 1500m dia PSC Pumping Main from Kalabgur to Patancheru at Ch. 86, near Angadipet Village 0.25 Circle-4 Division-8 15-May-08 Progress
10 Rectification of heavy leakage and removing and fixing of 300mm dia Sluice Valve for Air Valve on 1500mm dia Ph.II PSC Pumping Main on 1500mm dia Ph.II PSC Pumping Main at Ch.31, near Kalabgur Campus 0.44 Circle-4 Division-8 15-May-08 Progress
11 Rectification of heavy leakage on 1500mm dia Ph.II PSC Pumping Main at Ch. 34, near Kalabgur Campus 0.28 Circle-4 Division-8 15-May-08 Progress
12 Rectification of heavy leakage due to pipe burst on 1500mm dia PSC Pumping Main Phase-II from Kalabgur to Patancheru at Ch. 460.0 near Kawalampet Village 0.85 Circle-4 Division-8 18-Jul-08 Progress
13 Rectification of heavy leakage from 1500mm dia PSC pipe barrel joints on MWSS Phase-II Pumping Main at Ch. 551, near Narsingrao Garden, Manufacture, Supply and Fixing of spindle rod for 600mm dia Scour Valve at Ch. 465.0 near Kawalampet Village 0.89 Circle-4 Division-8 18-Jul-08 Progress
14 Supply, Delivery and Replacing of 600mm dia Butterfly Valve in place of damaged CI Valve on back washing line MWSS Phase-IV WTP at Peddapur 3.00 Circle- Division-   Tender Process
15 Filling the Pot-holes in BT Road from Peddapur Campus Main Gate to National Highway No: 9 2.50 Circle- Division- 15-May-08 Tender Process
16 Supply and Delivery of Alumina Sulphate (Ferric Alum) to Phase-I, II, III IV:, WTP 83.50 Circle- Division- 17-Jul-08 Tender Process