Krishna Drinking Water Supply Project Phase-III

In view of increased water supply demand, the Krishna Phase-III project was sanctioned by the Government vide GO Ms.325 MA&UDD, dated: 24-8-2012, at a cost of Rs.1670 Crores to bring 90 Mgd from Krishna river.

The financial tie up was arranged with Rs.1500 Crores loan from HUDCO with the Government counter guarantee and the balance Rs.170 Crores from State Government Budget support.

The major component works are almost completed except one segment length of pipeline along PVNR Expressway in the city.

Pipeline packages – 6 Packages 4 packages 100% completed (ie 107 Km)2 Ring Main packages (63.5Km)–60.04 Km completed. Balance 3.45 Km.The Ring Main-2 of 28.13 Km is completedThe Ring Main-1 – 31.548 Km completed out of 35 Km. Balance 3.45 Km programmed for completion by June’2015.
Reservoirs – 1 Package 7 Nos - Completed
Pump Houses – 1 Package 4 Nos - Completed
Pumps & Motors – 1 Package Pumps, Motors, and Transformers erection completed
WTP – 1 Package 45 Mgd completed by April’2015 Balance 45 Mgd by 30th June’2015

Project partially commissioned for 45 Mgd in April’2015 and the 90 Mgd will be supplied with full commissioning by June’2015.

 

 